Project Details

24" Main Oil Line Construction Contract (Yemen)

Posted by Admin in December, 2001
  1. Client: CANADIAN NEXEN PETROLEUM YEMEN
  2. Awarded Date: December, 2001
  3. Completion Date: June, 2002

Project Details

Project Scope : Construction, Pipelines, Wellhead, Tie-Ins, Welding, Civil Construction.

Canadian Nexen (CanOxy) awarded HAWK INTERNATIONAL to construct 24" O.D. x 0.381" W.T. Grade X70 bypass for Main Oil Line pipeline.

The general scope of work provided for the bypass installation, labour, equipment, tools, supervision, services and facilities required to complete construction and pre-commissioning of 24" bypass Main Oil Line.

Scope for this 24" pipeline included 8 km of rock blasting below grade, right of way construction, bending, hauling, stringing, welding, pre-heating/inter-pass, intelligent pigging and non-destructive testing.

There was also some procurement involvement specially blasting materials that needs to be transported and escorted plus full planning services, quality control and engineering work including site survey, routing and as-built documentation.